WORKLOAD PLANNING

DAILY PLAN

Calculate hours needed at a target efficiency of 0.67.

HOURS NEEDED—
Target efficiency0.67
Loaders needed—
1st shift runs—
2nd shift runs—

Hours = (Runs + Diversions) ÷ 0.67 + 0.5 × Backhauls

Loaders = hours ÷ 8. Shift split: 65% / 35%, with first shift rounded down and the remainder assigned to second shift.

ACTUAL PERFORMANCE

LOAD EFFICIENCY

Enter your workload and total hours worked.

LOAD EFFICIENCY—

Efficiency = (Runs + Diversions) ÷ (Hours − 0.5 × Backhauls)